Billing Overview

The following summarizes the estimated billing for JWTC's emergency snow and ice removal operations for the City of Baltimore, February 1 through February 12, 2026. Equipment hours are based on deployed equipment counts as reported to and acknowledged by DPW throughout the operation, applied at contract rates.

Final billing will reflect reconciled timesheet data upon completion of the payroll reconciliation process currently underway.


Contract Rates

Equipment Hourly Rate Contract Reference
Skid Steer (w/ operator) $225.00 Original Contract
Front-End Loader (w/ operator) $325.00 Original Contract
Dump Truck (w/ operator) $175.00 Amendment 1
Salt Truck (w/ operator) $180.00 Per DPW direction*
Field Supervisor $550.00/day Per DPW direction*

Salt trucks and supervisors operated at DPW's direct request throughout the event. Amendment 2 was acknowledged by DPW but not yet executed.


Daily Equipment Deployment & Billing

Date Skid Steers Dump Trucks Loaders Salt Trucks Supervisors Est. Daily Total
Feb 1 (Sat) 20 2 4 $50,800
Feb 2 (Sun) 71 4 $193,900
Feb 3 (Mon) 297 24 5 6 4 $1,771,720
Feb 4 (Tue) 240 44 9 1 6 $1,558,620
Feb 5 (Wed) 272 50 11 3 8 $1,781,960
Feb 6 (Thu) 361 60 15 9 10 $2,362,780
Feb 7 (Fri) 340 80 15 15 12 $2,360,400
Feb 8 (Sat) 325 85 20 12 12 $2,326,440
Feb 9 (Sun) 295 81 15 10 12 $2,100,000
Feb 10 (Mon) 310 88 18 10 12 $2,233,800
Feb 11 (Tue) 300 92 18 10 12 $2,196,600
Feb 12 (Wed) 200 50 10 5 8 $583,400

Feb 1–2: Mobilization phase (partial day operations). Feb 3–11: Full 24-hour operations (two 12-hour shifts). Feb 12: Demobilization per DPW directive (10-hour day).


Billing Summary by Equipment Type

Equipment Type Total Equipment-Hours Rate Estimated Total
Skid Steers 68,812 hrs $225/hr $15,482,700
Dump Trucks 14,996 hrs $175/hr $2,624,300
Front-End Loaders 3,124 hrs $325/hr $1,015,300
Salt Trucks 1,894 hrs $180/hr $340,920
Field Supervisors 104 days $550/day $57,200
Estimated Total $19,520,420

Additional Items Pending Reconciliation

The following items are not yet included in the estimate above and will be reflected in the final invoice:


Equipment Count Sources

Daily equipment counts were reported to DPW at multiple intervals throughout the operation (7:00 AM, 2:00 PM, and 6:00 PM as established by DPW). Key confirmed data points include:

Equipment counts for days between confirmed data points are interpolated based on mobilization patterns and the operational record.


Notes

This is a preliminary estimate provided in advance of final payroll reconciliation. The final invoice will reflect verified timesheet data reconciled against field records and DPW's operational tracking.

JWTC is committed to a transparent reconciliation process and welcomes discussion of any line items.


Estimated Total: $19,520,420

Final invoice expected to be in the range of $19.5–20.5 million following reconciliation of remaining timesheet data and inclusion of additional billable items noted above.